Sponsors

Congenital heart centre completed at the LRI

MTX has recently completed a new two-storey modular building at Leicester Royal Infirmary for University Hospitals of Leicester NHS Trust to house the East Midlands Congenital Heart Centre, with the £4.5 m project completed in 52 weeks.

Working in conjunction with its design partners, MTX designed and produced a bespoke 1,080 m² building, which links into the existing hospital. It houses an operating theatre, a catheter lab, recovery suites, outpatient and diagnostics facilities, ancillary facilities, and  a dedicated plant room. The theatre and catheter lab were constructed on the first floor using a modular-framed traditional cast-in situ concrete floor. This steel structure was upgraded to minimise vibration when the floor and ceiling mounted C-arms are in use.

The design of the facility included the provision of an  IPS/UPS system which serves the theatre, recovery beds, and catheter lab, and was interfaced to back up the Philips imaging equipment in the event of a power cut. The IPS circuits are interlaced to provide N+1 resilience, while the UPS system was designed to provide one-hour autonomy in the event of normal supply being lost.

A full suite of medical gases – including oxygen, nitrous oxide, medical air, surgical air, medical vacuum, and AGSS, was provided via a series of retractable and articulated pendants in both the operating theatre and cath lab. These were carefully co-ordinated with both floor and ceiling mounted C-arms in the catheter lab, to ensure that the room could function both as a catheter lab and an operating theatre. Independent simplex AGSS pumps were provided to each theatre, alongside a spare pump for back-up. A dry riser was installed within the staircase to ensure that all parts of the building were accessible to the first service.

MTX said: “All of the ground floor was installed as a traditional volumetric modular building. This allowed our M&E contractors to fit out the first fix M&E containment in the factory, prior to the components arriving on site. The air-handling units were also fabricated off site and dropped into place in the basement plant room, prior to the installation of the building.”

The new facility achieved a BREEAM score of ‘Very Good’ and an airtightness of 5.2, while U-values are compliant with Approved Document L2B. MTX  says it ‘faced the challenge of rescuing a project on the verge of collapse, because it could not be brought to fruition within budget’. It said: “We took a Stage 3 traditional concrete frame building and redesigned it as a steel-framed hybrid structure, bringing it back into budget through value engineering design and standardised elements.

“As the first floor was to accommodate a cardiac theatre and catheter lab, we could not compromise on the structural performance. The hybrid design allowed the use of pre-finished concrete cassettes on the ground floor, and a steel-framed offsite steel MMC solution on the

first floor, with a traditional cast in situ slab. The lightweight steel framed structure and brick slip façade reduced the overall size of the piled foundation, reducing costs, while still achieving the desired look.”

Latest Issues